Refurbishment Update

Pauline Jansen - August 9, 2022

As we near closer to the planned date for Block 2 to be finished there has been plenty of progress. Thankfully the wet weather hasn't created too many delays for the team.

Over the last couple of weeks we have seen:

  • All of the gib-board linings completed inside
  • Veranda roof installed
  • Metal cladding and flashings completed externally
  • New lowered ceiling gird was installed for the new ceiling panels
  • Gib stopping has started
  • A new fire and alarm system was connected as well as a fire board was installed in the administration area

Alongside this work, you may have also seen some much-awaited landscaping jobs and tree work done around the access to the school to prevent further sewage disruption from tree roots and also a direct line-of sight from the road to the new-fire panel which is a building requirement.