Property Update (May)

Gavin Burn —

An update from our project manager David Kolien ...

"The refurbishment of the new library and staff room building and the new administration building are progressing well and should be ready for the school to move into at the end of June. The footpaths and landscaping outside these buildings have been remodelled and are also close to completion. 

The final phase of the project has commenced early (with some work on the ground floor of the existing administration block) as these are converted and refurbished into new learning spaces for Years 1 and 2. 

The redevelopment of  the school is well on track to be completed this December, one month earlier than expected. The project team is very grateful for your patience so far – there’s not much longer to go now!”

David Kolien

Project Manager

The Building Intelligence Group