Northland Transport Alliance

KHS Editor —

NTA will be installing new traffic islands starting 5th January with work to be completed by 1st February. The platforms will be completed over 2 weekends with road closures on Kamo Road (6/7/8 Jan and 13/14/15 Jan) with the rest of the works being completed during the week with minor disruption to traffic flows until the end of January.

The crossings will be installed in the vicinity of Kamo Mowers and along Kamo Road around the Griffin Street area. There will be detours in place at certain times during this period.

This work will help keep our students safe by providing formalised crossings at key points along Kamo Road.