Property Update - Week 8

Jacqueline Wee —

Progress over past period:

  • Below slab services Block N completed.
  • New mechanical underground heating pipe installation to Block N complete.
  • Hardfill and sandblinding to Block N complete.
  • Formwork for Block N slab in progress.
  • Wall framing to Block 2 caretaker shed wall openings complete.
  • Stormwater and wastewater drainage around Block 2 complete.
  • Block N slab concrete pour scheduled for 15th march 2024.


Planned progress over next four weeks:

  • Structural Steel Delivery and install.
  • Lift shaft block work.
  • New concrete nib and channel drain works to Block 2.
  • External wall and roof framing to Block 2.
  • Remaining demolition of Block 2 block wall.
  • New roof for Block 2 caretakers shed.