Progress over past period:
- Below slab services Block N completed.
- New mechanical underground heating pipe installation to Block N complete.
- Hardfill and sandblinding to Block N complete.
- Formwork for Block N slab in progress.
- Wall framing to Block 2 caretaker shed wall openings complete.
- Stormwater and wastewater drainage around Block 2 complete.
- Block N slab concrete pour scheduled for 15th march 2024.
Planned progress over next four weeks:
- Structural Steel Delivery and install.
- Lift shaft block work.
- New concrete nib and channel drain works to Block 2.
- External wall and roof framing to Block 2.
- Remaining demolition of Block 2 block wall.
- New roof for Block 2 caretakers shed.