Property Update 2024

Jacqueline Wee —

Term 1 Week 1

Progress over past period:

  • Reinforcing and formwork for Block N foundation in progress.
  • Service trenching from Block N to Block C and asphalt work complete.
  • Demolition of Block 2 annex completed.
  • Concrete footing for the retaining wall on GL-A completed and Blockwork commenced.
  • New service trenching from Boiler room to Block 2 commenced.
  • Lift shaft blockwork completed.
  • Remediation of Block G temporary external wall completed.
  • Additional excavation and backfilling suggested by Geotech engineer.
  • Reinforcing and formwork for Block N foundation commenced.
  • Water supply investigation for Block 2 completed and isolation valve installed.
  • Class B asbestos removal complete.
  • Service trenching from Block N to Block C commenced.

What’s next:

  • Block N foundation works – DPM, formwork, reinforcing and concrete pour.
  • Tanking to lift shaft blockwork.
  • Below slab services installation.
  • Develop and submit ARCP for Class A asbestos removal in Block 2.
  • New mechanical, power and security to Block 2.
  • New concrete nib and channel drain works to Block 2.
  • External Framing to Block 2.
  • Remaining demolition of Block 2 block wall.
  • New sump and stormwater connection around Block 2.
  • New roof framing for Block 2 caretakers shed.