Term 1 Week 1
Progress over past period:
- Reinforcing and formwork for Block N foundation in progress.
- Service trenching from Block N to Block C and asphalt work complete.
- Demolition of Block 2 annex completed.
- Concrete footing for the retaining wall on GL-A completed and Blockwork commenced.
- New service trenching from Boiler room to Block 2 commenced.
- Lift shaft blockwork completed.
- Remediation of Block G temporary external wall completed.
- Additional excavation and backfilling suggested by Geotech engineer.
- Reinforcing and formwork for Block N foundation commenced.
- Water supply investigation for Block 2 completed and isolation valve installed.
- Class B asbestos removal complete.
- Service trenching from Block N to Block C commenced.
What’s next:
- Block N foundation works – DPM, formwork, reinforcing and concrete pour.
- Tanking to lift shaft blockwork.
- Below slab services installation.
- Develop and submit ARCP for Class A asbestos removal in Block 2.
- New mechanical, power and security to Block 2.
- New concrete nib and channel drain works to Block 2.
- External Framing to Block 2.
- Remaining demolition of Block 2 block wall.
- New sump and stormwater connection around Block 2.
- New roof framing for Block 2 caretakers shed.