New drains and preparation for concreting around the back of the  Kōmingo block with 9 weeks until completion of the school redevelopment.
 
Photo by Oaklands Redevelopment

Our school gardens and orchard will get a make-over, with input from students.

Oaklands Redevelopment —

It's 8 weeks until our redevelopment ends and thought is being given to landscaping.

This includes the garden and orchard area behind the Kōmingo red block. Students are involved in choosing the plants and trees. The school chickens will also return to the grounds - placed where the old bike stands were behind the Kōmingo block.

Inside the red brick blocks (Kōmingo at the junior part of the school, and Rururtu near the Yr 7/8 hub) painting and gibbing work continues this week.

Inside the Kōmingo block with 8 weeks until completion. — Image by: Oaklands Redevelopment
Inside the Kōmingo block in August 2020. — Image by: Oaklands Redevelopment