Rebuild timeline

Oaklands Redevelopment —

When new parts of the school will be finished and existing parts refurbished.

Redevelopment timeline

  • Started at the beginning of 2019
  • Will take almost two years.
  • First part finished in Term 3, 2019. The former office will be turned into a new learning space. (Highlighted in yellow on plan)
  • Second part finished in Term 4. A new classroom where the old junior playground stood. (Highlighted in green)
  • By the start of 2020, the new office, (highlighted in pink)  plus the new library, which also includes a teaching space (highlighted in blue) will be complete.  
  • Refurbishing existing buildings will start and finish in 2020. 

If you have a question about the redevelopment, email rebuild@oaklands.school.nz