Rebuild timeline
When new parts of the school will be finished and existing parts refurbished.
Redevelopment timeline
- Started at the beginning of 2019
- Will take almost two years.
- First part finished in Term 3, 2019. The former office will be turned into a new learning space. (Highlighted in yellow on plan)
- Second part finished in Term 4. A new classroom where the old junior playground stood. (Highlighted in green)
- By the start of 2020, the new office, (highlighted in pink) plus the new library, which also includes a teaching space (highlighted in blue) will be complete.
- Refurbishing existing buildings will start and finish in 2020.
If you have a question about the redevelopment, email rebuild@oaklands.school.nz