Property update

The Raroan —

Rooms 13-16 will move out of their temporary accommodation and will start Term 3 in their renovated classrooms in block three. 

The major building project including building the new learning street, upgrades to DPE rooms and upgrades to block 3 classrooms is due to be 100% completed by August 11th. At the beginning of Term 3 five out of the seven classrooms will be occupied. The four classrooms at the top of block three will be completed and ready to use so rooms 13, 14, 15 and 16 will be able to move out of their temporary rooms and  start the new term in the upgraded classrooms. DPE staff will also have the use of DPE 1&2. The learning street and DPE 3&4 will be ready by the end of week three. The following week will be a move in and set up time for DPE staff with full programme operating from these spaces following that.

Once the Learning Street is complete there will be open days during school time and an opportunity outside of school time to come in and see the new space in action.

HALL ROOF - All scoping for a temporary fix has been completed and the Ministry has given the go ahead for a temporary fix which will give us use of the hall until the end of the year. After which time the temporary roof will be replaced by a new roof.

 Work will start on Monday (11th July) and will take 14 fine working days to complete - keep fingers crossed for fine weather and we may have it back early next term.