Rebuild Update

Mr Chris Jones —

Peforming Arts Centre (PAC)

  • Work is continuing on reinforcing foundations – last part of outer ring poured 22 February – under floor works continue.
  • Reinstatement work underway with re-roofing of music rooms.
  • Flooring substructure reinstated under music rooms.
  • Re-roofing of the existing PAC building to commence week of 4 March.

PAC Extension

  • Slight holdup with supplies from the aluminium joiner but overall work progressing positively.
  • Internal wiring continues.
  • Both internal and external linings are underway.
  • Most of the aluminium joinery fitted and glaziers adding glass from this week.

Chapel

  • Successful topping pour of Chapel floor.  The floor will now harden off over 10 days before the grinding commences prior to being sealed – it will then be covered for protection before receiving a final polish closer to the build completion.
  • Work due to start in the next two weeks on the restoration of the old stained glass windows.
  • Main steps have now been poured.
  • Sacristy/Office area wall and roof framing well advanced.
  • Ply to the Chapel roof is progressing well and roofing is due to commence 4 March.
  • Exterior Terracotta cladding due to commence  week of 4 March.