Rebuild Update
Peforming Arts Centre (PAC)
- Work is continuing on reinforcing foundations – last part of outer ring poured 22 February – under floor works continue.
- Reinstatement work underway with re-roofing of music rooms.
- Flooring substructure reinstated under music rooms.
- Re-roofing of the existing PAC building to commence week of 4 March.
PAC Extension
- Slight holdup with supplies from the aluminium joiner but overall work progressing positively.
- Internal wiring continues.
- Both internal and external linings are underway.
- Most of the aluminium joinery fitted and glaziers adding glass from this week.
Chapel
- Successful topping pour of Chapel floor. The floor will now harden off over 10 days before the grinding commences prior to being sealed – it will then be covered for protection before receiving a final polish closer to the build completion.
- Work due to start in the next two weeks on the restoration of the old stained glass windows.
- Main steps have now been poured.
- Sacristy/Office area wall and roof framing well advanced.
- Ply to the Chapel roof is progressing well and roofing is due to commence 4 March.
- Exterior Terracotta cladding due to commence week of 4 March.