Construction Updates

Mr Chris Jones —

PAC and Chapel

PAC & Extension

  • New Toilets have been lined and stopping has commenced
  • Installation of soffit’s has recommenced
  • Installation of seismic joint is almost complete
  • Last sub-floor concrete pour is completed and back filled – floor slab reinstatement is underway
  • Stage store area well underway
  • Reinstatement of Auditorium and stage floor is ongoing and scaffold for the Auditorium ceiling seismic upgrade has commenced
  • New roof is completed – work on butynol and new roof hatch will start soon
  • Sewer and storm water lines to the east of the PAC have been installed

Chapel

  • Window frame installation has commenced
  • Sacristy glazing has been installed
  • Main ceiling installation, ceiling grid, and initial services installation have all commenced
  • Gallery bleachers have been constructed
  • Storm water systems have been installed around the Chapel exterior