Construction Updates
PAC and Chapel
PAC & Extension
- New Toilets have been lined and stopping has commenced
- Installation of soffit’s has recommenced
- Installation of seismic joint is almost complete
- Last sub-floor concrete pour is completed and back filled – floor slab reinstatement is underway
- Stage store area well underway
- Reinstatement of Auditorium and stage floor is ongoing and scaffold for the Auditorium ceiling seismic upgrade has commenced
- New roof is completed – work on butynol and new roof hatch will start soon
- Sewer and storm water lines to the east of the PAC have been installed
Chapel
- Window frame installation has commenced
- Sacristy glazing has been installed
- Main ceiling installation, ceiling grid, and initial services installation have all commenced
- Gallery bleachers have been constructed
- Storm water systems have been installed around the Chapel exterior