Northern Corridor Road Works

Christchurch City Council —

A update on progress and road closures.

Belfast Road will be closed to eastbound traffic from Monday 30 July until the end of October. This is so the new Belfast Bridge can joined to the road. When Belfast Road is open again you will be driving over the new bridge and the motorway will be built underneath. (A detour and more info are on the attached flyer.)

Night work on QEII Drive tonight (Friday 27 July) They will be removing some barriers and the container walkway tonight. This will mean stop / go overnight and some noise if you are a local (flyer attached).

On Wednesday morning 18 July, you will find the layout of the Cranford / Innes Intersection changed.

New line markings will temporarily shift lanes to give us room to excavate and install cables underground. The footpath at the north-west corner will be temporarily closed. See the attached flyer for more info.