Building Project Update

Lucy Naylor —

At Level 3 building works restarted with a revised program of works. It is exciting to see the plans coming to life and the project getting underway again.

Phase One: Room 7 and 8

The modernisation of Room 7 and 8 is well underway it is anticipated that Room 7 will be moving into their new classroom on 9 June. 

Phase Two: Room 4,5 and 6

Work will begin in Room 4,5 and 6 on 10 June. During the 6 week program of works these classes will be relocated. 

Phase Three: Administration Block 

Remediation work to the subfloor will be taking place 

Phase Four: Room 1,2 and 11

The upgrade of the Y0/1 classes, including new carpets, will be carried out between 27 July and 28 August. 

We appreciate the building works are disruptive and far from ideal given our current circumstances. However, we are working closely with the contractor to ensure disruptions are kept to a minimum, and learning continues uninterrupted.

 If your child's class is being relocated we will be in touch closer to the scheduled time to let you know how and when this will be happening.