Building Update
Hall and Admin Block
The concrete paths are now complete and a new septic tank has been installed. Final works include Quality Assurance stuff- final clean up, concrete splatter, some finishes, drain covers and levelling of surrounding grass areas.
Gardens need to be reinstated.
Junior Classes
Former Rooms 3&4 are looking vastly improved. Finishing touches to decks, ramps and stairs are underway with painting having been delayed by bad weather. We hope to have these rooms ready for use from the 19th of this month.
New Classrooms
3 New rooms are to be brought onsite. These will be new the Ministry of Education Modular design. A double classroom will run along the fenceline by the playcentre and a single one will be positioned adjacjent to the bus park in the driveway. The buildings will link up with decking and create a nice junior courtyard accomodating the sandpit and facing the tennis courts. The new buildings are expected in October/November.
Siteworks to tidy up the grounds where the Library was is to be re-levelled and reseeded after a couple of attempts that were ruined by all the heavy rain.
It will be great to have the weathertightness work done and dusted!